1,200-Tonne Steel Structure Shipment Departs For Surabaya — Indonesia's Largest Prefabricated Cold Storage Logistics Park

Jul 16, 2026

Leave a message

DALIAN, China - On July 14, 2026, 48 containers carrying 1,200 tonnes of fabricated structural steel departed Dalian Port aboard a bulk carrier bound for Tanjung Perak Port in Surabaya, Indonesia. The shipment forms the structural skeleton of an 18,000 m² multi-temperature cold storage logistics park - currently the largest prefabricated steel cold chain facility under construction in East Java.

 

Three Structural Challenges, Three ZSL Solutions

The facility operates across three temperature zones (-25°C / 0–4°C / 15–18°C), which pushed the design beyond standard industrial building norms:

Challenge Why It Matters ZSL Solution
Thermal bridge condensation 32°C / 85% RH tropics vs. -25°C frozen zone = condensation at purlin-panel interface Continuous thermal break strips at every connection, verified by thermal modeling
Seismic resilience Surabaya = Seismic Zone 4 (SNI 1726), 500-year event required Ductile connection detailing + reinforced panel zones at all beam-to-column joints
Marine-industrial corrosion Tanjung Perak = salt air + industrial emissions, 25-year design life Zinc-rich epoxy ≥ 80μm + high-build epoxy MIO ≥ 150μm, C4 rating

 

Delivery Coordination

The 1,200-tonne shipment was divided into 12 erection sequences, with each container packed to match site assembly order - eliminating on-site sorting, reducing crane idle time, and enabling 180–200 tonnes/week assembly. Structural completion targeted within 10 weeks of first container arrival. A ZSL site supervisor will be deployed to Surabaya for the first three weeks.

 

 💡 Your project timeline drives our logistics plan.

       Tell us your required on-site start date and target completion window. We'll build a container-by-container delivery schedule with sequenced packing - so your erection team never waits for steel. 

                