SHENYANG, China - A senior procurement and engineering delegation from a major Saudi Arabian industrial development group completed an intensive three-day technical audit at the Shenyang Zishenlong manufacturing facility this week.
Audit Scope
The client's evaluation for their 45,000 m² logistics hub project (requiring ~2,800 tonnes of fabricated steel) covered five areas:
| Audit Area | What They Verified | Result |
|---|---|---|
| Raw material traceability | Q355B heat certificates traced to mill batches | Pass - full chemical composition verified |
| Welding procedure | Live WPS qualification + macro-etch examination | Pass - zero fusion defects |
| Coating performance | ASTM B117 salt-spray: 1,500+ hours to first rust | Pass - exceeded 1,000-hour requirement |
| Dimensional accuracy | 5 random columns measured against tolerance tables | Pass - all within ±1.5mm |
| Container loading protocol | Edge protection, moisture barrier, weight distribution | Pass - aligned with Saudi port requirements |
Outcome
The audit concluded with a vendor qualification certificate. The client has requested detailed shop drawings and a phased delivery schedule for the first 800 tonnes, targeted for Q4 2026 shipment via Dalian to King Abdulaziz Port, Dammam.
This visit marks the sixth international client to conduct an on-site factory audit at ZSL in 2026.
💡 See the factory before you sign the contract.
We welcome on-site audits. If travel is not feasible, request a live video walkthrough of our production lines - guided by a ZSL engineer who answers your questions in real time.
Send Inquiry