What Issues Should Be Considered When Designing The Structural Layout Of A Steel-framed Factory Building?

Jan 19, 2026

Leave a message

In the design of the two rigid frames for the steel structure factory building, we arranged the secondary structures such as roof purlins, wall purlins, wind bracing columns, roof bracing, and wall bracing.


The following issues should be considered during the arrangement:


For roof bracing:
1. The roof bracing of portal frame factory buildings should form a geometrically stable truss system with the inclined beams.
2. In each temperature zone or construction phase section of the building, an independent spatial stable support system should be provided.
3. The larger the column spacing, the larger the crane lifting capacity, and the higher the working level, the greater the stiffness of the bracing should be.
4. In seismic zones, the bracing should be appropriately increased, and its node construction should be strengthened.
5. Roof bracing generally adopts a cross-bracing form and can be designed only as an axial tension member, without considering the work of the compression member. In non-seismic zones, round steel sections can be considered for bracing. In this case, since the steel ends are equipped with special tensioning devices, the slenderness ratio does not need to be controlled. In seismic zones or when wind loads are large, shaped steel sections are generally used for bracing. Bracing is generally controlled by the slenderness ratio, and when the load is large, the material strength should also be checked according to the internal force situation.
6. Tie rods are generally designed as compression members, and the commonly used section form is a round rod section.


For column bracing:
1. Column bracing should be provided in each column row of each unit of the steel structure factory building, and the side columns and middle column rows should be in the same bay.
2. When there is a crane, upper column bracing and lower column bracing should be provided above and below the corbel, respectively.
3. When the seismic fortification intensity is 8 degrees or there is a bridge crane, upper column bracing should be provided in the end bays of the steel structure factory building unit.
4. Ordinary horizontal tie rods should be provided at the top of each column of the steel structure factory building.

 

5

 

Send Inquiry